What is not a typical project management activity?

  1. Client liaison

  2. Setting the firm's profit goals

  3. Setting a project budget

  4. Maximizing productivity

The correct answer is: Setting the firm's profit goals

Setting the firm's profit goals is not considered a typical project management activity. In project management, the focus primarily revolves around the successful planning, execution, and completion of specific projects, which includes managing timelines, costs, resources, and stakeholder communications. While profit goals are crucial for a firm's overall strategic direction and fiscal health, they are typically determined at a higher management level rather than during the day-to-day management of individual projects. On the other hand, client liaison is a fundamental activity in project management, as maintaining effective communication with clients ensures that their requirements and expectations are met throughout the project lifecycle. Setting a project budget is also a core part of project management, as it directly influences how resources are allocated and how financial constraints are managed. Finally, maximizing productivity is essential in project management to ensure that tasks are completed efficiently and effectively, thus meeting project deadlines and achieving overall objectives.